MANAGEMENT OFFICE, KINGS CHELSEA - WEEKLY REPORT
Week commencing 04/09/2023
Deliveries:
Monday - concrete
Planned Works:
Monday 04 September 2023 - Friday 08 September 2023
Continuation of groundworks to management suite build
Cavity wall construction in progress
Plot 2 - excavation for reinforced concrete raft footings complete. Reinforce mesh in situ
for concrete pour on Monday morning.
Notes:
Site cabins/welfare set-up completed on Friday 24th March 2023.
Site cabins/welfare relocated to new position on Tuesday 13th June 2023.