WORK SCHEDULE

(Updated Noise Level Charts)
  • Monday 4 September - Friday 8th September
MANAGEMENT OFFICE, KINGS CHELSEA - WEEKLY REPORT
Week commencing 11/09/2023 Deliveries: 
Monday 11 September 2023 - Friday 18 September 2023 
Cavity wall construction in progress 
Notes: Site cabins/welfare set-up completed on Friday 24th March 2023. Site cabins/welfare relocated to new position on Tuesday 13th June 2023.
MANAGEMENT OFFICE, KINGS CHELSEA - WEEKLY REPORT
Week commencing 04/09/2023 Deliveries:
Monday - concrete Planned Works: Monday 04 September 2023 - Friday 08 September 2023 
Continuation of groundworks to management suite build 
Cavity wall construction in progress 
Plot 2 - excavation for reinforced concrete raft footings complete. Reinforce mesh in situ for concrete pour on Monday morning. 
Notes: Site cabins/welfare set-up completed on Friday 24th March 2023. Site cabins/welfare relocated to new position on Tuesday 13th June 2023.