WORK SCHEDULE 

(Updated Noise Level Charts)

Management Office, Kings Chelsea - Weekly Report

Week commencing 18/06/2023  Deliveries: TBC  Planned WorksMonday 18th June 2023 - Friday 22nd June 2023 Continuation of groundworks to management suite build Installation of pipework to temporary toilets that are to be used by Guildmore/Ogden Pitt. Preparation works for piling (excavating ground for piling blanket)  Notes: Site cabins/welfare set-up completed on Friday 24th March 2023. Site cabins/welfare relocated to new position on Tuesday 13th June 2023
Week commencing 05/06/2023  Deliveries: N/A  Planned Works: Monday 5th June 2023 - Friday 9th June 2023  Groundworks - installation of cables in duct underneath dog compound. NG Tunnelling to cap off new manhole found in footprint of the building. Reinstate dog compound to final position  Notes: Site cabins/welfare set-up completed on Friday 24th March 2023