Management Office, Kings Chelsea - Weekly Report

On Thursday, 24th August, we had a site inspection visit by Vasi of RBKC. 

The Block & Beam installation has been signed off, and internal foul drainage also has been signed off. 

Slurry mix finish to the B & B floor 90% complete 
To complete when Air Brick installation progresses by Tuesday, 29th August. 
Internal block work to DPC 80% complete 

WC 29th August: 
Plot 1. Completion of 125 cavity walls to DPC level 
Internal blockwork above DPC to start, followed by external brick facework with brick ties. [ Wed 30th] 
External surface water drainage is to be completed by Friday, 1st September. 
Reinstate kerbstones. 
Introduce hard standing as a temporary road surface. 

WC 29th August: Plot 2. 
Break ground and excavate for raft footings. 
Install steel reinforcing mesh. Pour concrete. 
Bon groundwork to progress Plot 2 to the DPC level 

Extensive deliveries and collections of materials and plant, culminating in site clearance by Bon 
At the end of the week. Bon off-site WC 4th September.” 

Management Office, Kings Chelsea - Weekly Report

Week commencing 21/08/2023 
Deliveries: Monday - delivery of blinding materials Wednesday - delivery of block and beam floors. 
Planned Works: Monday 21 August 2023 - Friday 25 August 2023 
Continuation of groundworks to management suite build Install of block and beam floor from Thursday onwards. 
Notes: Site cabins/welfare set-up completed on Friday 24th March 2023. 
Site cabins/welfare relocated to new position on Tuesday 13th June 2023.

Management Office, Kings Chelsea - Weekly Report

Week commencing 14/08/2023 
Deliveries: TBC 
Planned Works: Monday 14 August 2023 - Friday 18 August 2023 
Continuation of groundworks to management suite build 
Backfill of ground beams - Monday 
Restore access road to be reopened from Tuesday onwards. 
Notes: Site cabins/welfare set-up completed on Friday 24th March 2023. 
Site cabins/welfare relocated to new position on Tuesday 13th June 2023.