The renovation of flat 13 Benham house

The works are agreed to start on Wednesday 8th February 2023 and to take approximately 16 weeks
BY:Xpert Construction LtdRegistered office address: Insito Finance Ltd Sabichi House, 5 Wadsworth Road, Perivale, United Kingdom, UB6 7JDCompany number 07720764, VAT number: 872207920 Mob: 07779 237845 E: basalatas@gmail.com
All works will be done in accordance with the guidelines set forth by the Kings Chelsea Estate and only be carried out from Monday to Friday within the allowed hours of 8am to 5pm and if needed on Saturdays between 8am and 12pm. 
As per the regulations in place, any noisier works will be carried out between 9am and 12pm and from 2pm to 5pm on week days only. 
If you have any questions or comments, please feel free to contact us. 
Clare Williams Interior Design info@clarewilliams.co.uk

Schedule of works13 Benham House Start date : 08/02/2023

08/02-19/02: Health and Safety training, Site induction, floors and units protection, removing redundant stuff, utility cabinets and living room cupboards 
20/02-12/03 Electrical work, joinery decorative panelling in living room, preparation for decorating 
13/02-26/03 Electrical work, joinery work, decorative panelling in second reception and study, decorating work. 
27/02-12/03 Replacing ceiling corners in hall, installing/replacing ceiling lights, preparing walls for wallpaper, decorating, 
13/03- 26/03 Kitchen units spraying, decorating, 
27/03-09/04 Joinery/cupboard work installations, decorating work 
10/04-23/04 Decorating work, mirrors installations, wall lights installation 
24/04-07/05 Floor sanding 
08/05-21/05 Wallpaper hanging, final decorating, final wall lights installation 
22/05 – 28/05 Snagging, curtains installation,